Practical Checklist: Migrating Workloads to Alibaba Cloud Without Surprises
MigrationAlibaba CloudHow-to

Practical Checklist: Migrating Workloads to Alibaba Cloud Without Surprises

UUnknown
2026-02-25
10 min read
Advertisement

Hands-on Alibaba Cloud migration checklist for devs and IT admins: networking, IAM, region strategy, compliance, testing, and lift-and-shift tips for 2026.

Practical Checklist: Migrating Workloads to Alibaba Cloud Without Surprises

Hook: If you’re an engineer or IT admin planning a migration to Alibaba Cloud, your biggest fear is downtime, hidden costs, or compliance red flags. This hands-on checklist cuts through the noise and gives you a repeatable plan for networking, IAM, compliance, region strategy, testing, and cutover — with concrete commands and examples you can run today.

Executive summary — What to do first

Start here: inventory everything, map dependencies, pick regions, and secure identity. If you only read one section, follow this high-level checklist before touching production:

  • Inventory & dependency mapping: apps, databases, connections, storage, network paths.
  • Region & compliance decision: select regions by latency, service availability and legal requirements (ICP, data residency).
  • Network design: VPC, subnets, route tables, security groups, CEN/Express Connect for hybrid links.
  • IAM & least privilege: RAM roles, policies, temporary credentials for migration jobs.
  • Data migration plan: tool selection (DTS, OSS sync, database replication), cutover window and rollback plan.
  • Testing & observability: performance, failover, smoke tests, CloudMonitor + Log Service integration.
  • Cost & sizing: instance families, disk types, reserved instances and spot options.

1. Discovery and planning — ground truth before you move

Migration failures almost always start with fuzzy inventories. Spend time mapping what you have and how components interact. Use automated tools and manual review.

Practical steps

  1. Run an application dependency map (APM): list services, ports, and upstream/downstream systems.
  2. Export VM and container specs: CPU, RAM, disk I/O, network throughput and GPU needs.
  3. Identify data gravity: where is the largest dataset? That drives region and network choices.
  4. Classify each workload: lift-and-shift, replatform, refactor. Prioritize low-risk lift-and-shift for initial waves.

Tools & commands

Use open-source tools and cloud-native utilities for discovery. Examples:

# example: export container images and configs for inventory (local step)
docker inspect --format='{{json .}}' my-app > my-app-inspect.json

# use aliyun CLI for account-level inventory (example: list ECS instances)
aliyun ecs DescribeInstances --RegionId cn-hangzhou

2. Region strategy — beyond latency

Choosing the right Alibaba Cloud region in 2026 means balancing latency, compliance and service availability. Late-2025 and early-2026 trends pushed providers — Alibaba included — to expand GPU, edge and hybrid connectivity. That makes region choice strategic, not just geographic.

Decision factors

  • Latency & user proximity: measure RTT from client populations to candidate regions.
  • Service parity: confirm critical services (GPU types, managed databases, serverless) are available in the region.
  • Compliance & data residency: Mainland China regions require ICP registration for public web services; cross-border transfer rules apply.
  • Hybrid connectivity: consider Express Connect + CEN for predictable, high-throughput links to your data centers.
  • Disaster recovery: choose AZs and multi-region pairs for RTO/RPO targets.

Quick checks

  • Run a simple ping and traceroute to each candidate region from representative client nodes.
  • Use the Alibaba Cloud console or API to list available instance types: some regions lag in new GPU or high-memory SKUs.

3. Networking checklist — VPC, CEN, Express Connect and CDN

Design your network for segmentation, secure access, and graceful failover. Treat the network as critical infrastructure: plan subnets, NAT, routing and connectivity.

Key components

  • VPC per environment: separate VPCs for dev, staging, and production. Use predictable CIDR ranges to avoid overlap in hybrid setups.
  • Subnets and routing: split public and private subnets by AZ. Configure route tables, SNAT for egress and DNAT for ingress as needed.
  • Security groups & network ACLs: apply least-privilege ingress/egress rules. Security groups are stateful; ACLs are stateless.
  • Private link & endpoint services: use VPC endpoints for OSS, RDS and other managed services to avoid public egress.
  • Hybrid links: Express Connect with CEN for multi-region enterprise networks; consider VPN as fallback.
  • CDN & WAF: front public apps with Alibaba CDN and WAF; for Mainland China sites, confirm ICP and CDN caching strategy.

Example Terraform snippet (VPC)

provider "alicloud" {
  region = "cn-hangzhou"
}

resource "alicloud_vpc" "main" {
  name       = "app-vpc"
  cidr_block = "172.16.0.0/16"
}

resource "alicloud_vswitch" "private" {
  vpc_id            = alicloud_vpc.main.id
  cidr_block        = "172.16.1.0/24"
  availability_zone = "cn-hangzhou-b"
}

4. IAM & security — adopt least privilege from day one

Alibaba Cloud uses RAM (Resource Access Management). For migrations, avoid using root account keys. Create focused roles and temporary credentials for migration processes.

Best practices

  • Use RAM roles: attach roles to ECS instances or ECS-based migration tools rather than embedding long-lived keys.
  • Least privilege: craft narrowly-scoped policies for migration tools (read-only for inventory, read-write for final sync).
  • Temporary credentials: use STS assumeRole for automation and CI/CD pipelines.
  • Audit & MFA: enable CloudAudit, require MFA for privileged users and break down policies across teams.

Sample RAM policy (JSON)

{
  "Version": "1",
  "Statement": [
    {
      "Effect": "Allow",
      "Action": [
        "ecs:DescribeInstances",
        "dts:Describe*",
        "oss:GetObject",
        "oss:PutObject"
      ],
      "Resource": "*"
    }
  ]
}

5. Data migration — minimize downtime with safe synchronization

Data migration is the riskiest part. Plan for continuous sync and a tested cutover. Alibaba Cloud's Data Transmission Service (DTS) and OSS tools are your friends for database and object data migration.

Strategy

  • Initial bulk copy: use OSS or offline import for very large datasets where network transfer is impractical.
  • Continuous replication: configure DTS for CDC (change data capture) to keep source and target in sync.
  • Cutover window: schedule a final write freeze or use application-level dual-write toggles for zero-downtime migrations.
  • Verify integrity: checksum validation and sampling of records before switching traffic.

Tools & commands

Typical tools include Alibaba DTS for databases, OSS (object storage) CLI sync, rsync for file-level, and database-native replication.

# example: upload a backup to OSS
aoss cp backup.tar.gz oss://my-bucket/backups/

# sample: start a DTS task (conceptual CLI flow)
aliyun dts CreateSubscriptionInstance --SourceEndpoint '...' --SubscriptionObject 'db.table'

6. Testing: the safety net

Testing proves your design. Cover at least the following: functional, performance, failover, security, and rollback validation. Include staging tests that mirror production network topology.

Test types & how-to

  • Smoke tests: basic routing and service sanity checks after each wave.
  • Integration tests: validate end-to-end flows including third-party APIs and caches.
  • Load & performance: run traffic tests using wrk, k6, or JMeter. Test both app and DB under expected and peak loads.
  • Failover/DR: simulate AZ and region failure, validate DNS TTLs, and automated failover procedures.
  • Security testing: run vulnerability scans and penetration tests; ensure WAF and CDN rules are operational.
  • Rollback drills: validate rollback steps end-to-end, including re-synchronizing data if needed.

Canary & staged rollouts

Use canary or blue/green deployments for application migration. For stateful services, prefer database replication + feature flags to toggle traffic.

7. Cutover and rollback plan

Define an explicit cutover playbook before you start. Include timing, communication, metrics to watch, and an immediate rollback path.

Cutover playbook checklist

  • Pre-cutover: final data sync & checksum verification.
  • Cutover step: switch DNS or load balancer and monitor error rates and latency.
  • Post-cutover: run full smoke test suite & validate data consistency.
  • Rollback criteria: error rate threshold, data integrity failure, or unacceptable latency. Document exact steps to revert traffic and resync.

8. Observability & post-migration operations

Visibility after migration equals control. Integrate CloudMonitor, Log Service, APM tools, and your existing dashboards.

Concrete actions

  • Enable CloudMonitor metrics for ECS, OSS, RDS and SLB.
  • Ship logs to Log Service or your existing SIEM; ensure structured logs and centralized retention policies.
  • Set SLOs and alert thresholds for latency, error rate and resource exhaustion.
  • Instrument synthetic checks (HTTP health, DB queries) from multiple regions.

9. Cost optimization & governance

Don't let cloud bills surprise you. Track costs early and enforce tagging and lifecycle rules.

Practical steps

  • Tag everything: team, project, environment and owner. Otherwise chargeback and optimization are impossible.
  • Choose pricing model: On-demand for testing, Subscription/Reserved for steady-state, Spot for batch/CI workloads.
  • Right-size post-migration: use utilization metrics to downsize oversized instances or move to better families.
  • Clean up unused resources: snapshots, unattached disks, idle IPs and test buckets.

Compliance needs in 2026 remain strict and region-specific. China’s regulatory landscape and cross-border transfer rules received renewed enforcement in 2025; make sure legal and security teams sign off before public-facing launches.

Items to confirm

  • ICP license: required for hosting public web services in Mainland China.
  • Data residency: ensure PII storage aligns with local laws and your internal policies.
  • Encryption: use KMS for envelope encryption of disks and OSS objects; track key ownership and rotation.
  • Contractual protection: review Alibaba Cloud SLA, DPA and cross-border data transfer clauses with legal counsel.

11. Automation & repeatability

Treat migration waves as code. Automate infrastructure and migration tasks so future waves are consistent and auditable.

Practical automation choices

  • Terraform for infra-as-code (alicloud provider).
  • CI pipelines for migration tasks, leveraging STS temporary credentials.
  • Use configuration management (Ansible/Chef) or container images for bootstrapping instances.
  • Automated smoke tests and Canary promotion scripts.

12. Advanced considerations for 2026

By 2026, common migration patterns include moving AI workloads to managed GPU instances, adopting hybrid multi-cloud connectivity, and using container orchestration across clouds. Keep these in mind:

  • AI & GPU: verify the right GPU types and driver support in your target region if you’re migrating ML workloads.
  • Multi-cloud tooling: consider Kubernetes federation, GitOps and service meshes to reduce vendor lock-in.
  • Edge & CDN: with rising edge demand, plan where to place caches and compute for real-time apps.
  • Data meshes & privacy-preserving compute: explore techniques like anonymization and regional processing to meet compliance without duplicating datasets.
Tip: Migrations succeed when teams rehearse rollback and observability, not when they perfectly predict every variable.

Actionable final checklist (copyable)

  1. Inventory: export list of instances, databases, buckets, networks.
  2. Map dependencies and classify workloads (lift-and-shift vs replatform).
  3. Select region(s) and confirm service availability & compliance (ICP if needed).
  4. Create VPCs & subnets with planned CIDR ranges; configure security groups and endpoints.
  5. Provision RAM roles and temporary STS credentials for automation.
  6. Plan data sync: initial bulk + DTS CDC for databases.
  7. Automate infra with Terraform; store state securely and use modules for repeatability.
  8. Execute staged migration: dev → staging → canary → prod; monitor with CloudMonitor & Log Service.
  9. Perform post-migration cutover tests and a fully-documented rollback drill.
  10. Right-size and implement cost governance and tagging.

Real-world case study (short)

A mid-sized SaaS provider I mentored executed a phased migration: they started with non-critical services using lift-and-shift, validated DTS replication to RDS (ApsaraDB) in a cn-hangzhou region, then cut application traffic using ALB and DNS TTLs. Their biggest win was automating rollback and observability — when a DB index caused a latency spike during cutover, they reverted traffic in 7 minutes using the documented playbook.

Final takeaways

  • Plan before you migrate: inventory and dependency mapping prevent most surprises.
  • Design for testing and rollback: rehearsal beats hope.
  • Automate and enforce governance: tags, IAM, and cost controls keep operations sustainable.
  • Regulatory checks are non-negotiable: in 2026, expect stricter enforcement and region-specific rules.

Call to action

Ready to run a risk-free pilot migration to Alibaba Cloud? Download our 1-page migration playbook (templates for Terraform, RAM policies, DTS setup and cutover scripts) and try a single-service lift-and-shift today. If you prefer tailored guidance, schedule a migration review with our cloud engineers — we’ll audit your inventory and provide a prioritized migration wave plan.

Advertisement

Related Topics